West Ahtanum Road Project Schedule

Most drivers have noticed the road construction project on West Ahtanum Road between Main Street & South 16th Avenue.  Information about the project:  the West Ahtanum Road Resurfacing project includes approximately 45,000 SY planing bituminous pavement; 6,310 tons HMA; pavement repair; pavement markings; and related improvements.  The grinding and paving portion will begin Wednesday, May 4, 2022  between 6 p.m. thru 6 a.m.   Below is a schedule to help you plan your route and avoid delays.

Grinding Schedule:          May 4th thru May 12th                  Beginning at 6 p.m. / ending at 6 a.m.

Intersection Paving:        May 9, 2022                                  Goodman Road & Longfibre Road

Intersection Paving:        May 10, 2022                                3rd Avenue

Paving Schedule:            May 15th thru May 30th                Beginning at 6 p.m. / ending at 6 a.m.

Finishing Schedule:        May 31st thru June 2nd                 Beginning at 6 p.m. / ending at 6 a.m.

Please contact Public Works & Community Development, at 509.225.3524, if you have any questions or comments.