The Valley Mall Boulevard Resurfacing Project began on April 1, 2019 and the anticipated completion date is June 10, 2019. To follow is the construction schedule:

  • Monday, May 13 thru Thursday, May 23 – week day evening road closures from 8 p.m. to 6 a.m. (entire length of the project)
  • Friday, May 24 – All lanes open; no construction work
  • Monday, May 27 – All lanes open; no construction work
  • Tuesday, May 28 thru Monday, June 10 – week day evening road closures from 8 p.m. to 6 a.m. (entire length of the project)